(Another) Big Push, Pull and Haul

IMPORTANT: We are aiming to splice the fibre to properties between the village and Mhor 84 starting from 15 May. So, if you’re a householder on that route, please make sure that you’ve got the drop tubing to your house in place and buried before then if you want to be connected, if this hasn’t already been done. We can’t guarantee when any properties that miss out this time will be connected.

For the last couple of months, the team has been working flat out to get the ducting in to enable us to get to the entire eastern end of the glen, from the village east to Mhor 84. 

After a huge push in late April to get the job done, last weekend saw the fibre blown into the final stretch from Auchleskine to the cabinet at the village hall. 

Continue reading (Another) Big Push, Pull and Haul

Christmas 2018 Update

After the splicing work in mid-December week we have 71 (36%) of all the properties in the glen connected, including Rhuveag, all of Craigruie and the Boathouse.  The full loop around Loch Voil is now complete, which enables us to start work on reaching the outlying properties towards Inverlochlarig and Immeroin. Monachyle Mhor is now at last online itself. Completion of the final backbone ducting from Auchtubh to Mhor 84 is just awaiting final agreement from BEAR Scotland, after which we can get our contractor to work on the road section of that dig. As soon as that’s complete, we can blow fibre east from the village and start splicing and connecting everything between Auchleskine and Mhor 84. Continue reading Christmas 2018 Update