Christmas 2018 Update

After the splicing work in mid-December week we have 71 (36%) of all the properties in the glen connected, including Rhuveag, all of Craigruie and the Boathouse.  The full loop around Loch Voil is now complete, which enables us to start work on reaching the outlying properties towards Inverlochlarig and Immeroin. Monachyle Mhor is now at last online itself. Completion of the final backbone ducting from Auchtubh to Mhor 84 is just awaiting final agreement from BEAR Scotland, after which we can get our contractor to work on the road section of that dig. As soon as that’s complete, we can blow fibre east from the village and start splicing and connecting everything between Auchleskine and Mhor 84. Continue reading Christmas 2018 Update